[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-887824":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},887824,574,1,"单选题","某省审批的矿产资源开发利用规划环境影响报告书编制完成后上报审查。根据《规划环境影响评价条例》，该省的下列做法中，正确的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","规划审批机关在审批该规划前，召集环境保护主管部门和专家组成审查小组，对环境影响报告书进行审查",false,{"key":16,"text":17,"correct":14},"B","规划审批机关在审批该规划后，召集环境保护主管部门和专家组成审查小组，对环境影响报告书进行审查",{"key":19,"text":20,"correct":21},"C","环境保护主管部门召集有关部门代表和专家组成审查小组，在该规划审批前，对环境影响报告书进行审查",true,{"key":23,"text":24,"correct":14},"D","环境保护主管部门召集有关部门代表和专家组成审查小组，在该规划审批后，对环境影响报告书进行审查","根据《规划环境影响评价条例》第十七条规定，设区的市级以上人民政府审批的专项规划，在审批前由其环境保护主管部门召集有关部门代表和专家组成审查小组，对环境影响报告书进行审查。审查小组应当提交书面审查意见。",{"id":6,"name":27,"category":28,"favorite":29},"环境影响评价相关法律法规","建筑工程",0]