[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-887823":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},887823,574,1,"单选题","根据《规划环境影响评价条例》，下列内容中，属于规划环境影响报告书审查意见应当包括的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","评价方法的适当性",true,{"key":16,"text":17,"correct":18},"B","评价内容的全面性",false,{"key":20,"text":21,"correct":18},"C","基础资料、数据的完整性",{"key":23,"text":24,"correct":18},"D","环境影响分析、预测和评估的客观性","根据《规划环境影响评价条例》第十九条规定，审查小组的成员应当客观、公正、独立地对环境影响报告书提出书面审查意见，规划审批机关、规划编制机关、审查小组的召集部门不得干预。审查意见应当包括下列内容：①基础资料、数据的真实性；②评价方法的适当性；③环境影响分析、预测和评估的可靠性；④预防或者减轻不良环境影响的对策扣措施的合理性和有效性；⑤公众意见采纳与不采纳情况及其理由的说明的合理性；⑥环境影响评价结论的科学性。",{"id":6,"name":27,"category":28,"favorite":29},"环境影响评价相关法律法规","建筑工程",0]