[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-887727":3},{"question":4,"library":27},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":25,"analysis":26},887727,573,2,"多选题","某炼化项目试生产3个月后委托有资质的单位开展竣工环境保护验收工作，需要现场验收检查（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","可行性研究报告",false,{"key":16,"text":17,"correct":18},"B","环保监测仪器设备",true,{"key":20,"text":21,"correct":18},"C","总排水口在线监测设备",{"key":23,"text":24,"correct":18},"D","企业环境管理制度","BCD","按照建设项目布局特点或工艺特点，安排现场检查，内容主要包括水、气、声（振动）、固体废物污染源及其配套的处理设施、排污口的规范化、环境敏感目标及相应的监测点位，在线监测设备监测结果，水土保持、生态保护、自然景观恢复措施等的实施效果。 核查建设项目环境管理档案资料，内容包括：环保组织机构、各项环境管理规章制度、施工期环境监理资料、日常监测计划（监测手段、监测人员及实验室配备、检测项目及频次）等。",{"id":6,"name":28,"category":29,"favorite":30},"环境影响评价技术方法","建筑工程",0]