[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-887724":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":24,"analysis":25},887724,573,2,"多选题","某铅酸蓄电池厂竣工环境保护验收通过的条件应包括（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","“三废”排放达标",true,{"key":16,"text":17,"correct":14},"B","敏感点特征污染物环境质量达标",{"key":19,"text":20,"correct":14},"C","铅排放总量符合环境批复要求",{"key":22,"text":23,"correct":14},"D","环评中提出的环保设施和污染防治措施落实到位","ABCD","建设项目竣工环境保护验收监测与调查的重点包括：①检查建设项目环境管理制度的执行和落实情况，各项环保设施或工程的实际建设、管理、运行状况以及各项环保治理措施的落实情况；②监测分析评价治理设施处理效果或治理工程的环境效益；③监测分析建设项目废水、废气、固体废物等排放达标情况和噪声达标情况；④监测必要的环境保护敏感点的环境质量；⑤监测统计国家规定的总量控制污染物排放指标的达标情况；⑥调查分析评价生态保护以及环境敏感目标保护措施情况。",{"id":6,"name":27,"category":28,"favorite":29},"环境影响评价技术方法","建筑工程",0]