[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-887723":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":24,"analysis":25},887723,573,2,"多选题","高速公路竣工环境保护验收调查报告中，下列要求正确的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","对不稳定的弃渣场，提出补救措施",true,{"key":16,"text":17,"correct":14},"B","对未恢复的取、弃土场、施工营地等临时用地，提出恢复的具体要求",{"key":19,"text":20,"correct":14},"C","异地开垦基本农田措施未完全落实，按“基本农田占一补一”原则尽快落实",{"key":22,"text":23,"correct":14},"D","环评报告书和批复文件中遗漏的环境敏感点，受公路影响噪声超标，要求进行跟踪监测，并提出解决方案","ABCD","《基本农田保护条例》第十六条规定，经国务院批准占用基本农田的，当地人民政府应当按照国务院的批准文件修改土地利用总体规划，并补充划入数量和质量相当的基本农田。占用单位应当按照占多少、垦多少的原则，负责开垦与所占基本农田的数量与质量相当的耕地；没有条件开垦或者开垦的耕地不符合要求的，应当按照省、自治区、直辖市的规定缴纳耕地开垦费，专款用于开垦新的耕地。",{"id":6,"name":27,"category":28,"favorite":29},"环境影响评价技术方法","建筑工程",0]