[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-887663":3},{"question":4,"library":27},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":25,"analysis":26},887663,573,2,"多选题","属于地下水评价Ⅱ类项目场地环境水文地质问题减缓措施的有（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","提出防止地下水超采措施",true,{"key":16,"text":17,"correct":18},"B","监测地下水水质变化",false,{"key":20,"text":21,"correct":14},"C","监测地下水水位变化",{"key":23,"text":24,"correct":14},"D","建立应对相关环境地质问题的应急预案","ACD","Ⅱ类建设项目地下水保护与环境水文地质问题减缓措施有：①以均衡开采为原则，提出防止地下水资源超量开采的具体措施，以及控制资源开采过程中由于地下水水位变化诱发的湿地退化、地面沉降、岩溶塌陷、地面裂缝等环境水文地质问题产生的具体措施；②建立地下水动态监测系统，并根据项目建设所诱发的环境水文地质问题制订相应的监测方案；③针对建设项目可能引发的其他环境水文地质问题提出应对预案。",{"id":6,"name":28,"category":29,"favorite":30},"环境影响评价技术方法","建筑工程",0]