[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-887662":3},{"question":4,"library":27},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":25,"analysis":26},887662,573,2,"多选题","新建化工项目环境风险防范措施包括（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","贮运的风险防范措施",true,{"key":16,"text":17,"correct":18},"B","项目施工的风险防范措施",false,{"key":20,"text":21,"correct":14},"C","总图布置的风险防范措施",{"key":23,"text":24,"correct":14},"D","自动控制的风险防范措施","ACD","环境风险的防范与减缓措施是在环境风险评价的基础上做出的。主要环境风险防范措施为：①选址、总图布置和建筑安全防范措施；②危险化学品贮运安全防范及避难所；③工艺技术设计安全防范措施；④自动控制设计安全防范措施；⑤电气、电讯安全防范措施；⑥消防及火灾报警系统；⑦紧急救援站或有毒气体防护站设计。B项，新建化工项目施工过程中的风险属于安全风险，不属于环境风险。",{"id":6,"name":28,"category":29,"favorite":30},"环境影响评价技术方法","建筑工程",0]