[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-887578":3},{"question":4,"library":27},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":25,"analysis":26},887578,573,2,"多选题","工矿企业声环境影响评价中，需着重分析（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","主要噪声源",true,{"key":16,"text":17,"correct":14},"B","厂界和功能区超标的原因",{"key":19,"text":20,"correct":14},"C","厂区总图布置的合理性",{"key":22,"text":23,"correct":24},"D","建设项目与相邻工程之间的关系",false,"ABC","工矿企业声环境影响评价应着重分析说明以下问题：①按厂区周围敏感目标所处的环境功能区类别评价噪声影响的范围和程度，说明受影响人口情况；②分析主要影响的噪声源，说明厂界和功能区超标原因；③评价厂区总图布置和控制噪声措施方案的合理性与可行性，提出必要的替代方案；④明确必须增加的噪声控制措施及其降噪效果。",{"id":6,"name":28,"category":29,"favorite":30},"环境影响评价技术方法","建筑工程",0]