[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-887489":3},{"question":4,"library":27},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":25,"analysis":26},887489,573,2,"多选题","环境噪声现状监测布点应考虑的因素有（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","固定声源情况",true,{"key":16,"text":17,"correct":14},"B","流动声源情况",{"key":19,"text":20,"correct":21},"C","地表植被",false,{"key":23,"text":24,"correct":14},"D","敏感点情况","ABD","环境噪声现状监测布点时应根据声源的不同情况采用不同的布点方法：①当声源为固定声源时，现状测点应重点布设在既可能受到现有声源影响，又受到建设项目声源影响的敏感目标处，以及有代表性的敏感目标处；②当声源为流动声源，且呈现线声源特点时，例如公路、铁路噪声，现状测点位置选取应兼顾敏感目标的分布状况、工程特点及线声源噪声影响随距离衰减的特点。",{"id":6,"name":28,"category":29,"favorite":30},"环境影响评价技术方法","建筑工程",0]