[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-887479":3},{"question":4,"library":27},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":25,"analysis":26},887479,573,2,"多选题","公路建设项目声环境现状调查的内容应包括评价范围内的（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","现有噪声源",true,{"key":16,"text":17,"correct":18},"B","风噪声",false,{"key":20,"text":21,"correct":14},"C","环境敏感目标",{"key":23,"text":24,"correct":14},"D","环境噪声背景值","ACD","公路、铁路为线路型工程，其声环境影响评价需着重分析、说明以下问题：①针对项目建设期和不同运行阶段，评价沿线评价范围内各敏感目标（包括城镇、学校、医院、几种生活区等），按标准要求预测声级的达标及超标状况，并分析受影响人口的分布情况。②对工程沿线两侧的城镇规划中受到噪声影响的范围绘制等声级曲线，明确合理的噪声控制距离和规划建设控制要求。③结合工程选线和建设方案布局，评述其合理性和可行性，必要时提出环境替代方案。④对提出的各种噪声防治措施需进行经济技术论证，在多方案比选后规定应采取的措施并说明措施降噪效果。",{"id":6,"name":28,"category":29,"favorite":30},"环境影响评价技术方法","建筑工程",0]