[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-887432":3},{"question":4,"library":27},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":25,"analysis":26},887432,573,2,"多选题","某一钢铁厂扩建项目，工程建设内容中包含有铁路专用线5km，环境噪声现状监测点应布设在（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","现有项目边界处",true,{"key":16,"text":17,"correct":14},"B","厂区周边的敏感点处",{"key":19,"text":20,"correct":14},"C","铁路专用线两侧敏感点处",{"key":22,"text":23,"correct":24},"D","现有厂内办公楼处",false,"ABC","布设的现状监测点应覆盖整个评价范围，包括厂界（或场界、边界）和敏感目标。评价范围内有明显的声源，并对敏感目标的声环境质量有影响，或建设项目为改扩建工程，应根据声源种类采取不同的监测布点原则。当声源为固定声源时，现状测点应重点布设在可能既受到现有声源影响，又受到建设项目声源影响的敏感目标处，以及有代表性的敏感目标处；为满足预测需要，也可在距离现有声源不同距离处设衰减测点。故该钢铁厂扩建项目的环境噪声现状监测点布设在现有项目边界处、厂区周边及铁路专用线两侧的敏感点处。",{"id":6,"name":28,"category":29,"favorite":30},"环境影响评价技术方法","建筑工程",0]