[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-887405":3},{"question":4,"library":27},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":25,"analysis":26},887405,573,2,"多选题","分析工业污染型项目总图布置方案合理性时，应考虑（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","项目选址",false,{"key":16,"text":17,"correct":18},"B","周围环境敏感点位置",true,{"key":20,"text":21,"correct":18},"C","气象、地形条件",{"key":23,"text":24,"correct":18},"D","污染源的位置","BCD","分析工业污染型项目总图布置方案合理性时，应考虑的内容有：①分析厂区与周围的保护目标之间所定卫生防护距离的可靠性；②根据气象、水文等自然条件分析工厂和车间布置的合理性；③分析对周围环境敏感点处置措施的可行性。",{"id":6,"name":28,"category":29,"favorite":30},"环境影响评价技术方法","建筑工程",0]