[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-887397":3},{"question":4,"library":27},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":25,"analysis":26},887397,573,2,"多选题","高速公路建设项目工程分析中，勘察期应重点关注（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","项目与沿线自然保护区的位置关系",true,{"key":16,"text":17,"correct":18},"B","施工方式和施工时间",false,{"key":20,"text":21,"correct":14},"C","与城镇规划的关系",{"key":23,"text":24,"correct":18},"D","交通噪声影响","AC","公路项目工程分析应涉及勘察设计期、施工期和运营期，以施工期和运营期为主。其中，勘察设计期工程分析的重点是选址选线和移民安置，详细说明工程与各类保护区、区域路网规划、各类建设规划和环境敏感区的相对位置关系及可能存在的影响；施工期是公路工程产生生态破坏和水土流失的主要环节，应重点考虑工程用地、桥隧工程和辅助工程(施工期临时工程)所带来的环境影响和生态破坏。",{"id":6,"name":28,"category":29,"favorite":30},"环境影响评价技术方法","建筑工程",0]