[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-887392":3},{"question":4,"library":27},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":25,"analysis":26},887392,573,2,"多选题","在评述建设项目清洁生产水平时，应分析（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","资源利用指标",true,{"key":16,"text":17,"correct":14},"B","污染物产生指标",{"key":19,"text":20,"correct":21},"C","环保治理工艺先进性",false,{"key":23,"text":24,"correct":14},"D","生产工艺先进性","ABD","依据生命周期分析的原则，环评中的清洁生产评价指标可分为六大类：①生产工艺与装备要求；②资源能源利用指标；③产品指标；④污染物产生指标；⑤废物回收利用指标；⑥环境管理要求。六类指标既有定性指标也有定量指标，资源能源利用指标和污染物产生指标在清洁生产审核中是非常重要的两类指标，因此，必须有定量指标，其余四类指标属于定性指标或者半定量指标。环保治理工艺先进性属于末端治理。",{"id":6,"name":28,"category":29,"favorite":30},"环境影响评价技术方法","建筑工程",0]