[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-887354":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},887354,573,1,"单选题","序批式活性污泥SBR除磷时，应该选取的污泥负荷和充水比是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","高污泥负荷、低充水比",false,{"key":16,"text":17,"correct":14},"B","低污泥负荷、低充水比",{"key":19,"text":20,"correct":21},"C","高污泥负荷、高充水比",true,{"key":23,"text":24,"correct":14},"D","低污泥负荷、高充水比","序批式活性污泥法（SBR）适用于建设规模为Ⅲ类、Ⅳ类、Ⅴ类的污水处理厂和中小型废水处理站，适合于间歇排放工业废水的处理。SBR反应池的数量不应少于2个。SBR以脱氮为主要目标时，应选用低污泥负荷，低充水比；以除磷为主要目标时，应选用高污泥负荷、高充水比。",{"id":6,"name":27,"category":28,"favorite":29},"环境影响评价技术方法","建筑工程",0]