[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-887349":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},887349,573,1,"单选题","输油管线工程建设过程中，减少工程施工对植被影响的重要措施是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","加快施工进度",false,{"key":16,"text":17,"correct":14},"B","减少施工机械数量",{"key":19,"text":20,"correct":14},"C","缩短作业时段",{"key":22,"text":23,"correct":24},"D","缩小作业带宽度",true,"施工期的生态影响因建设项目性质不同和项目所处环境特点的不同会有很大的差别。在建设项目环境影响评价时需要根据具体情况做具体分析，提出有针对性的施工期环境保护工作建议。建立规范化操作程序和制度，以一定程序和制度的方式规范建设期的行为，是减少生态影响的重要措施。例如，公路、铁路、管线施工中控制作业带宽度，可大大减少对周围地带的破坏和干扰，尤其在草原地带，控制机动车行道范围，防止机动车在草原上任意选路行驶，是减少对草原影响的根本性措施。",{"id":6,"name":27,"category":28,"favorite":29},"环境影响评价技术方法","建筑工程",0]