[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-887259":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},887259,573,1,"单选题","机场建设项目环境影响评价中，为防治飞机噪声污染，应优先分析的是（ ）",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","机场飞行架次调整的可行性",false,{"key":16,"text":17,"correct":14},"B","机场周边环境保护目标隔声的数量",{"key":19,"text":20,"correct":14},"C","机场周边环境保护目标搬迁的数量",{"key":22,"text":23,"correct":24},"D","机场位置、跑道方位选择、飞行程序和城市总体规划的相容性",true,"题中，“为防治飞机噪声污染”，由导则10.3.4，机场噪声防治措施，a）通过不同机场位置、跑道方位、飞行程序方案的声环境影响预测结果，分析敏感目标受影响的程度，提出优化的机场位置、跑道方位、飞行程序方案建议。故选D。",{"id":6,"name":27,"category":28,"favorite":29},"环境影响评价技术方法","建筑工程",0]