[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-887233":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},887233,573,1,"单选题","某河渠长1000m，两侧与浅层地下水联系密切且补给地下水，已知潜水含水层渗透系数100m／d，地下水力坡度0.5％，水力坡度取值段含水层平均厚度4m，则该河渠对地下水渗漏补给量是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","1000m3／D",false,{"key":16,"text":17,"correct":14},"B","2000m3／D",{"key":19,"text":20,"correct":14},"C","3000m3／D",{"key":22,"text":23,"correct":24},"D","4000m3／D",true,"当河渠水位变化幅度较小时，河渠一侧的渗漏补给量可以用达西公式计算：Q渗=KLIh。本题中，河流一侧渗漏补给量Q=K?L?I?h=100×1000×0.5％×4=2000m3／d。如果河渠两侧的水文地质条件一样，河渠渗漏量应是计算结果的两倍。所以两侧渗漏补给量为4000m3／d。",{"id":6,"name":27,"category":28,"favorite":29},"环境影响评价技术方法","建筑工程",0]