[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-887193":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},887193,573,1,"单选题","某项目设计的循环水量为25000m3\u002Fd，循环补水量为400m3\u002Fd，其他新鲜用水量为2600m3\u002Fd，该项目的水重复利用率为（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","0.814",false,{"key":16,"text":17,"correct":18},"B","0.893",true,{"key":20,"text":21,"correct":14},"C","0.902",{"key":23,"text":24,"correct":14},"D","0.986","重复利用率=重复用水量\u002F（新鲜水+重复用水量）=25000\u002F（400+2600+25000）=89.3%，其中循环水补水为隐藏新鲜水。",{"id":6,"name":27,"category":28,"favorite":29},"环境影响评价技术方法","建筑工程",0]