[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-887161":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},887161,573,1,"单选题","建设项目环境影响识别中，必须包括的阶段是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","项目选址期",false,{"key":16,"text":17,"correct":18},"B","建设期和运营期",true,{"key":20,"text":21,"correct":14},"C","项目初步设计期",{"key":23,"text":24,"correct":14},"D","产业链规划期","建设项目环境影响识别中，拟建项目的“活动”，一般按四个阶段划分，即：建设前期（勘探、选址选线、可研与方案设计）、建设期、运行期和服务期满后，需要识别不同阶段各“活动”可能带来的影响。其中建设期和运营期（施工期和运营期）是任何项目均包含的阶段，必须进行环境影响识别。",{"id":6,"name":27,"category":28,"favorite":29},"环境影响评价技术方法","建筑工程",0]