[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-887152":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},887152,573,1,"单选题","某隧道工程穿超石灰岩地区，在环境影响评价中应特别重视（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","水文地质条件",true,{"key":16,"text":17,"correct":18},"B","隧道长度",false,{"key":20,"text":21,"correct":18},"C","出渣量",{"key":23,"text":24,"correct":18},"D","爆破方式","施工期工程分析时，应注意管道不同的穿越方式可造成不同影响。采用隧道穿越方式，除产生隧道工程弃渣外，还可能对隧道区域的地下水和坡面植被产生影响；若有施工爆破则产生噪声、振动影响，甚至局部地质灾害。因此，隧道工程穿超石灰岩地区，在环境影响评价中应特别重视水文地质条件。",{"id":6,"name":27,"category":28,"favorite":29},"环境影响评价技术方法","建筑工程",0]