[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-887151":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},887151,573,1,"单选题","矩阵法环境影响识别表中，建设项目各建设阶段与环境要素交叉的格点，表示的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","影响因子",false,{"key":16,"text":17,"correct":14},"B","影响范围",{"key":19,"text":20,"correct":21},"C","影响要素",true,{"key":23,"text":24,"correct":14},"D","影响程度","矩阵法是通过系统地列出拟建项目各阶段的各项“活动”，以及可能受拟建项目各项“活动”影响的环境要素，构造矩阵确定各项“活动”和环境要素及环境因子的相互作用关系。在矩阵法环境识别表中，如果认为某项“活动”可能对某一环境要素产生影响，则在矩阵相应交叉的格点将环境影响标注出来。因此，格点代表的是影响要素。",{"id":6,"name":27,"category":28,"favorite":29},"环境影响评价技术方法","建筑工程",0]