[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-887106":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},887106,573,1,"单选题","下列方法中，不适用于新建项目大气污染源调查的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","类比调查法",false,{"key":16,"text":17,"correct":14},"B","设计资料确定法",{"key":19,"text":20,"correct":14},"C","物料衡算法",{"key":22,"text":23,"correct":24},"D","现场实测法",true,"污染源调查与分析方法根据不同的项目可采用不同的方式，一般对于新建项目可通过类比调查、物料衡算或设计资料确定；对于评价范围内的在建和未建项目的污染源调查，可使用已批准的环境影响报告书中的资料；对于现有项目和改、扩建项目的现状污染源调查，可利用已有有效数据或进行实测；对于分期实施的工程项目，可利用前期工程最近5年内的验收监测资料、年度例行监测资料或进行实测。",{"id":6,"name":27,"category":28,"favorite":29},"环境影响评价技术方法","建筑工程",0]