[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-887052":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},887052,573,1,"单选题","某拟建项目排放口的上游有一榨糖厂，仅旱季生产6个月，该糖厂允许COD排放量为180吨\u002F年。点源调查时确认该糖厂旱季贡献的COD排放负荷是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","10吨\u002F月",false,{"key":16,"text":17,"correct":14},"B","15吨\u002F月",{"key":19,"text":20,"correct":21},"C","30吨\u002F月",true,{"key":23,"text":24,"correct":14},"D","45吨\u002F月","本题中，该糖厂旱季贡献的COD排放负荷=年排放量÷生产月数=180÷6=30（吨\u002F月）。",{"id":6,"name":27,"category":28,"favorite":29},"环境影响评价技术方法","建筑工程",0]