[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-887020":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},887020,573,1,"单选题","某新建公路拟经过国家重点保护植物集中分布地，工程方案中应优先考虑的保护措施是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","迁地保护",false,{"key":16,"text":17,"correct":14},"B","育种种植",{"key":19,"text":20,"correct":14},"C","货币补偿",{"key":22,"text":23,"correct":24},"D","选线避让",true,"该工程属于生态影响类的建设项目，应按照避让、减缓、补偿和重建的次序提出生态影响防护与恢复的措施；所采取措施的效果应有利修复和增强区域生态功能。题中所给新建公路项目，经过国家重点保护植物集中分布地时会造成一定的生态影响，因此工程方案中应优先考虑的保护措施是选线避让。货币补偿不属于措施范畴。",{"id":6,"name":27,"category":28,"favorite":29},"环境影响评价技术方法","建筑工程",0]