[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-886995":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},886995,573,1,"单选题","西南山区某拟建风电场，其选址位于候鸟迁徙通道上，为避免风电场建设对候鸟迁徙造成影响，应优先采取的措施是( )。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","减少风机高度",false,{"key":16,"text":17,"correct":14},"B","减少占地面积",{"key":19,"text":20,"correct":14},"C","减少风机数量",{"key":22,"text":23,"correct":24},"D","风电场另行选址",true,"另行选址是最优措施，选址变了，影响也没了。",{"id":6,"name":27,"category":28,"favorite":29},"环境影响评价技术方法","建筑工程",0]