[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-886982":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},886982,573,1,"单选题","地下水环境影响评价中，属于 II 类项目地下水保护对策的是( )。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","场地地面防渗",false,{"key":16,"text":17,"correct":14},"B","产污单元源头控制",{"key":19,"text":20,"correct":14},"C","场地地下水污染物浓度监测",{"key":22,"text":23,"correct":24},"D","场地地下水水位动态观测",true,"其他三个选项主要针对I类项目地下水保护对策。",{"id":6,"name":27,"category":28,"favorite":29},"环境影响评价技术方法","建筑工程",0]