[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-886949":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},886949,573,1,"单选题","现有工程检修期间，某敏感点环境噪声背景值为 50 dB (A) ，现有工程和扩建工程声源对敏感点的贡献值分别为 50 dB (A) 53 dB (A) ，该敏感点的预测值为( ) dB (A)",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","56",true,{"key":16,"text":17,"correct":18},"B","53",false,{"key":20,"text":21,"correct":18},"C","51",{"key":23,"text":24,"correct":18},"D","50","噪声值相同时相加，声级增加 3dB (A) ，因此，本题不用公式计算应可知答案为A",{"id":6,"name":27,"category":28,"favorite":29},"环境影响评价技术方法","建筑工程",0]