[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-886919":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},886919,573,1,"单选题","当建设项目对生态敏感保护目标可能产生影响时，采取的最好保护措施是( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","避让",true,{"key":16,"text":17,"correct":18},"B","补偿",false,{"key":20,"text":21,"correct":18},"C","c. 迁移",{"key":23,"text":24,"correct":18},"D","隔离","",{"id":6,"name":27,"category":28,"favorite":29},"环境影响评价技术方法","建筑工程",0]