[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-886812":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},886812,573,1,"单选题","当项目的经济内部收益率( )行业基准收益率时，表示该项目是可行的。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","小于",false,{"key":16,"text":17,"correct":14},"B","大于或等于",{"key":19,"text":20,"correct":14},"C","c. 等于",{"key":22,"text":23,"correct":24},"D","大于",true,"",{"id":6,"name":27,"category":28,"favorite":29},"环境影响评价技术方法","建筑工程",0]