[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-886785":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},886785,573,1,"单选题","风险评价需要从各功能单元的( )风险中，选出危害最大的作为本项目的最大可信灾害事故，并以此作为风险可接受水平的分析基础。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","最大可信事故",true,{"key":16,"text":17,"correct":18},"B","95%可信事故",false,{"key":20,"text":21,"correct":18},"C","c. 最小可信事故",{"key":23,"text":24,"correct":18},"D","98%可信事故","",{"id":6,"name":27,"category":28,"favorite":29},"环境影响评价技术方法","建筑工程",0]