[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-886430":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},886430,573,1,"单选题","某建设项目水平衡图如下图所示(单位m3\u002Fd) ，.项目的间接冷却水循环率为( )",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","75.0%",true,{"key":16,"text":17,"correct":18},"B","78.8%",false,{"key":20,"text":21,"correct":18},"C","81.5%",{"key":23,"text":24,"correct":18},"D","83.9%","根据间接冷却水循环率的公式:间接冷却水循环率=间接冷却水循环量\u002F (间接冷却水循环量+间接冷却水系统取水量)，间接冷却水循环量为600m3\u002Fd ，间接冷却水系统取水量为 200 m3\u002Fdo",{"id":6,"name":27,"category":28,"favorite":29},"环境影响评价技术方法","建筑工程",0]