[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-886375":3},{"question":4,"library":27},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":25,"analysis":26},886375,572,2,"多选题","依据《建设项目竣工环境保护验收技术规范—生态影响类》，某铁矿项目竣工环境保护验收调查中，其工程概况调查内容包括（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","地理位置",true,{"key":16,"text":17,"correct":14},"B","项目组成",{"key":19,"text":20,"correct":14},"C","项目工程量",{"key":22,"text":23,"correct":24},"D","项目立项时间和审批部门",false,"ABC","工程概况调查应明确建设项目所处的地理位置、项目组成、工程规模、工程量、主要经济或技术指标（可列表）、主要生产工艺及流程、工程总投资与环境保护投资（环境保护投资应列表分类详细列出）、工程运行状况等。工程建设过程中发生变更时，应重点说明其具体变更内容及有关情况。",{"id":6,"name":28,"category":29,"favorite":30},"环境影响评价技术导则与标准","建筑工程",0]