[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-886307":3},{"question":4,"library":27},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":25,"analysis":26},886307,572,2,"多选题","根据《规划环境影响评价技术导则》，规划方案的环境影响预测与评价的内容有（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","规划开发强度分析",true,{"key":16,"text":17,"correct":14},"B","影响预测与评价",{"key":19,"text":20,"correct":14},"C","累积环境影响预测与分析",{"key":22,"text":23,"correct":24},"D","经济效益分析",false,"ABC","根据《规划环境影响评价技术导则—总纲》（HJ 130—2014），环境影响预测与评价的内容：①规划开发强度分析；②影响预测与评价；③累积环境影响预测与分析；④资源与环境承载力评估。",{"id":6,"name":28,"category":29,"favorite":30},"环境影响评价技术导则与标准","建筑工程",0]