[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-886257":3},{"question":4,"library":27},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":25,"analysis":26},886257,572,2,"多选题","建设项目（除线性工程外）可依据（ ）确定土壤环境影响现状调查评价范围。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","污染途径",true,{"key":16,"text":17,"correct":14},"B","气象条件",{"key":19,"text":20,"correct":21},"C","植被覆盖",false,{"key":23,"text":24,"correct":14},"D","地形地貌","ABD","根据《环境影响评价技术导则—土壤环境（试行）》（HJ 964—2018），建设项目（除线性工程外）土壤环境影响现状调查评价范围可根据建设项目影响类型、污染途径、气象条件、地形地貌、水文地质条件等确定并说明。",{"id":6,"name":28,"category":29,"favorite":30},"环境影响评价技术导则与标准","建筑工程",0]