[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-886243":3},{"question":4,"library":27},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":25,"analysis":26},886243,572,2,"多选题","土壤环境影响评价中工作等级为三级的建设项目，在预测时可采用的方法包括（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","标准指数法",false,{"key":16,"text":17,"correct":14},"B","定量分析法",{"key":19,"text":20,"correct":21},"C","定性描述法",true,{"key":23,"text":24,"correct":21},"D","类比分析法","CD","根据《环境影响评价技术导则—土壤环境（试行）》（HJ 964—2018），土壤环境影响评价工作等级为三级的建设项目，在预测与评价时可采用定性描述或类比分析法进行预测。",{"id":6,"name":28,"category":29,"favorite":30},"环境影响评价技术导则与标准","建筑工程",0]