[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-886094":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},886094,572,1,"单选题","生态影响调查结论与建议中，总结的内容主要是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","建设项目对环境影响评价文件及环境影响评价审批文件要求的落实情况",true,{"key":16,"text":17,"correct":18},"B","建设项目对环境保护行政主管部门颁布的法律法规执行情况",false,{"key":20,"text":21,"correct":18},"C","建设项目执行环境保护标准的情况",{"key":23,"text":24,"correct":18},"D","建设项目对环保措施的投入运行情况","调查结论是全部调查工作的结论，编写时需概括和总结全部工作。总结的内容包括：①主要总结建设项目对环境影响评价文件及环境影响评价审批文件要求的落实情况；②重点概括说明工程建设成后产生的主要环境问题及现有环境保护措施的有效性，在此基础上，对环境保护措施提出改进措施和建议；③根据调查和分析的结果，客观、明确地从技术角度论证工程是否符合建设项目竣工环境保护验收条件。",{"id":6,"name":27,"category":28,"favorite":29},"环境影响评价技术导则与标准","建筑工程",0]