[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-886078":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},886078,572,1,"单选题","根据工程建设过程，不属于验收调查时段的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","工程前期",false,{"key":16,"text":17,"correct":14},"B","施工期",{"key":19,"text":20,"correct":14},"C","试运行期",{"key":22,"text":23,"correct":24},"D","服务期满后",true,"根据工程建设过程，验收调查时段一般分为工程前期、施工期、试运行期三个时段。",{"id":6,"name":27,"category":28,"favorite":29},"环境影响评价技术导则与标准","建筑工程",0]