[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-886074":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},886074,572,1,"单选题","对于公路、铁路、轨道交通等线性工程以及港口项目，验收调查应在工况稳定、生产负荷达到近期预测生产能力（或交通量）（ ）以上的情况下进行。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","70%",false,{"key":16,"text":17,"correct":18},"B","75%",true,{"key":20,"text":21,"correct":14},"C","80%",{"key":23,"text":24,"correct":14},"D","90%","对于公路、铁路、轨道交通等线性工程以及港口项目，验收调查应在工况稳定、生产负荷达到近期预测生产能力（或交通量）75%以上的情况下进行。",{"id":6,"name":27,"category":28,"favorite":29},"环境影响评价技术导则与标准","建筑工程",0]