[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-886064":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},886064,572,1,"单选题","验收调查标准原则上采用建设项目（ ）经环境保护部门确认环境保护标准与环境保护设施工艺指标来进行验收的。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","环境影响评价阶段",true,{"key":16,"text":17,"correct":18},"B","环境影响评价文件",false,{"key":20,"text":21,"correct":18},"C","环境敏感目标变化",{"key":23,"text":24,"correct":18},"D","工程实际建设文件","验收调查标准原则上采用建设项目环境影响评价阶段经环境保护部门确认的环境保护标准与环境保护设施工艺指标进行验收，对已修订新颁布的环境保护标准应提出验收后按新标准进行达标考核的建议。",{"id":6,"name":27,"category":28,"favorite":29},"环境影响评价技术导则与标准","建筑工程",0]