[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-886040":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},886040,572,1,"单选题","危险废物建设项目环境影响评价应对建设项目（ ）进行分析评价。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","建设期",false,{"key":16,"text":17,"correct":14},"B","投产运营期",{"key":19,"text":20,"correct":14},"C","服务期满后",{"key":22,"text":23,"correct":24},"D","全过程",true,"对建设项目危险废物的产生、收集、贮存、运输、利用、处置全过程进行分析评价，严格落实危险废物各项法律制度，提高建设项目危险废物环境影响评价的规范化水平，促进危险废物的规范化监督管理。",{"id":6,"name":27,"category":28,"favorite":29},"环境影响评价技术导则与标准","建筑工程",0]