[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-886007":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},886007,572,1,"单选题","根据《危险废物填埋污染控制标准》，危险废物填埋场地下水位应在不透水层（ ）m以下，否则须提高防渗设计标准。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","1",false,{"key":16,"text":17,"correct":18},"B","3",true,{"key":20,"text":21,"correct":14},"C","5",{"key":23,"text":24,"correct":14},"D","6","根据《危险废物填埋污染控制标准》（GB 18598—2001），填埋场场址的地质条件应符合下列要求：①能充分满足填埋场基础层的要求；②现场或其附近有充足的黏土资源以满足构筑防渗层的需要；③位于地下水饮用水水源地主要补给区范围之外，且下游无集中供水井；④地下水位应在不透水层3m以下，否则，必须提高防渗设计标准并进行环境影响评价，取得主管部门同意；⑤天然地层岩性相对均匀、渗透率低，其渗透系数应符合《危险废物填埋污染控制标准》（GB 18598—2001）中“6.4填埋场天然基础层的饱和渗透系数不应大于1.0×10—5cm\u002Fs，且厚度不应小于2m”；⑥地质结构相对简单、稳定，没有断层。",{"id":6,"name":27,"category":28,"favorite":29},"环境影响评价技术导则与标准","建筑工程",0]