[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-885952":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},885952,572,1,"单选题","下列有关规划环境影响识别的说法错误的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","如果规划分为近期、中期、远期或其他时段，应选择其中重要的一个时段进行影响识别",true,{"key":16,"text":17,"correct":18},"B","识别规划实施的有利影响或不良影响，重点识别可能造成的重大不良环境影响",false,{"key":20,"text":21,"correct":18},"C","应识别规划实施产生的污染物与人体接触的途径、方式（如经皮肤、口或鼻腔等），以及可能造成的人群健康影响",{"key":23,"text":24,"correct":18},"D","以图、表等形式，建立规划要素与资源、环境要素之间的动态响应关系","A项，重点从规划的目标、规模、布局、结构、建设时序及规划包含的具体建设项目等方面，全面识别规划要素对资源和环境造成影响的途径与方式，以及影响的性质、范围和程度。如果规划分为近期、中期、远期或其他时段，还应识别不同时段的影响。",{"id":6,"name":27,"category":28,"favorite":29},"环境影响评价技术导则与标准","建筑工程",0]