[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-885934":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},885934,572,1,"单选题","依据《规划环境影响评价技术导则—总纲》，下列有关规划环境影响评价的原则叙述错误的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","评价应在规划纲要编制阶段（或规划启动阶段）介入",false,{"key":16,"text":17,"correct":14},"B","重点分析规划实施对生态系统产生的整体影响和综合效应",{"key":19,"text":20,"correct":21},"C","评价的重点内容和专题设置范围必须大于规划对环境影响的性质、程度和范围",true,{"key":23,"text":24,"correct":14},"D","评价选择的基础资料和数据应真实、有代表性","根据《规划环境影响评价技术导则—总纲》（HJ 130—2014），规划环境影响评价原则包括：①全程互动原则；②一致性原则；③整体性原则；④层次性原则；⑤科学性原则。其中，一致性原则是指评价的重点内容和专题设置应与规划对环境影响的性质、程度和范围相一致，应与规划涉及领域和区域的环境管理要求相适应。",{"id":6,"name":27,"category":28,"favorite":29},"环境影响评价技术导则与标准","建筑工程",0]