[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-885871":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},885871,572,1,"单选题","根据《环境影响评价技术导则—生态影响》，三级评价项目基本图件不包括（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","项目区域地理位置图",false,{"key":16,"text":17,"correct":14},"B","工程平面图",{"key":19,"text":20,"correct":14},"C","土地利用现状图",{"key":22,"text":23,"correct":24},"D","植被类型图",true,"根据《环境影响评价技术导则—生态影响》（HJ 19—2011），三级评价项目基本图件包括：①项目区域地理位置图；②工程平面图；③土地利用现状图；④典型生态保护措施平面布置示意图。",{"id":6,"name":27,"category":28,"favorite":29},"环境影响评价技术导则与标准","建筑工程",0]