[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-885849":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},885849,572,1,"单选题","根据《环境影响评价技术导则—生态影响》，工程分析中应重点调查的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","勘察期和施工期",false,{"key":16,"text":17,"correct":14},"B","勘察期和退役期",{"key":19,"text":20,"correct":21},"C","施工期和运营期",true,{"key":23,"text":24,"correct":14},"D","运营期和退役期","根据《环境影响评价技术导则—生态影响》（HJ 19—2011），工程分析时段应涵盖勘察期、施工期、运营期和退役期，以施工期和运营期为调查分析的重点。",{"id":6,"name":27,"category":28,"favorite":29},"环境影响评价技术导则与标准","建筑工程",0]