[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-885842":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},885842,572,1,"单选题","根据《环境影响评价技术导则—生态影响》，铅锌矿开采项目工程分析时段应涵盖（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","勘察期、施工期、运营期和退役期",true,{"key":16,"text":17,"correct":18},"B","施工期、运营期和退役期",false,{"key":20,"text":21,"correct":18},"C","施工期和运营期",{"key":23,"text":24,"correct":18},"D","施工期","根据《环境影响评价技术导则—生态影响》（HJ 19—2011）的规定，工程分析内容应包括：项目所处的地理位置、工程的规划依据和规划环评依据、工程类型、项目组成、占地规模、总平面及现场布置、施工方式、施工时序、运行方式、替代方案、工程总投资与环保投资、设计方案中的生态保护措施等。工程分析时段应涵盖勘察期、施工期、运营期和退役期，以施工期和运营期为调查分析的重点。",{"id":6,"name":27,"category":28,"favorite":29},"环境影响评价技术导则与标准","建筑工程",0]