[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-885725":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},885725,572,1,"单选题","根据《建筑施工场界环境噪声排放标准》，关于施工期间噪声等效声级测量的说法，正确的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","测量连续20min的等效声级",true,{"key":16,"text":17,"correct":18},"B","测量连续1h的等效声级",false,{"key":20,"text":21,"correct":18},"C","测量全部施工作业时段的等效声级",{"key":23,"text":24,"correct":18},"D","测量昼间16h、夜间8h的等效声级","建筑施工场界环境噪声的测量时段：稳态噪声测量1min的等效声级，非稳态噪声测量20min的等效声级。施工期间产生的噪声是非稳态，所以需要检测20min的等效声级。",{"id":6,"name":27,"category":28,"favorite":29},"环境影响评价技术导则与标准","建筑工程",0]