[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-885694":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},885694,572,1,"单选题","建设项目声环境影响评价时段可分为（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","施工期和运行期",true,{"key":16,"text":17,"correct":18},"B","运行近期、中期、远期",false,{"key":20,"text":21,"correct":18},"C","运行期和竣工期",{"key":23,"text":24,"correct":18},"D","施工期和竣工期","建设项目声环境影响评价时段可分为施工期、运行期两个时段评价。建设项目运行期声环境评价时段分为：①固定声源，将固定声源投产运行后作为环境影响评价时段。②流动声源，将工程预测的代表性时段（一般分为运行近期、中期、远期）分别作为环境影响评价时段。",{"id":6,"name":27,"category":28,"favorite":29},"环境影响评价技术导则与标准","建筑工程",0]