[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-885638":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},885638,572,1,"单选题","根据《环境影响评价技术导则—地下水环境》，下列地下水评价工作等级为二级的建设项目中，应开展枯、丰二期地下水水位监测的有（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","位于沙漠分布区的建设项目",false,{"key":16,"text":17,"correct":14},"B","位于丘陵山区分布区的建设项目",{"key":19,"text":20,"correct":14},"C","位于岩溶裂隙分布区的建设项目",{"key":22,"text":23,"correct":24},"D","位于山前冲（洪）积分布区的建设项目",true,"ABC三项，沙漠地区、丘陵山区、岩溶裂隙等的二级评价项目应开展一期地下水水位监测；D项，山前冲（洪）积的二级评价项目应开展枯、丰二期地下水水位监测。",{"id":6,"name":27,"category":28,"favorite":29},"环境影响评价技术导则与标准","建筑工程",0]